VICE PRESIDENT YEMI OSIBANJO SAN (GCON) COMMISSIONS NEW NDPHC AND NEWS ENGINEERING  (NIG) LTD,s NEW POWER SUBSTATION IN ANAMBRA STATE

VICE PRESIDENT YEMI OSIBANJO SAN (GCON) COMMISSIONS NEW NDPHC AND NEWS ENGINEERING (NIG) LTD,s NEW POWER SUBSTATION IN ANAMBRA STATE

On Tuesday, 24th August, 2021, a new 2x60MVA, 132/33KVA substation was commissioned in Awka, Anambra state by the Vice President. The Commissioning event was also graced by the Anambra State Governor Mr Willie Obiano, Mr Chiedu Ugbo (Managing Director/CEO Niger Delta Power Holding Company Limited), Mr Ifeoluwa Oyedele (Executive Director Networks, Niger Delta Power Holding Comapny Ltd) as well Mr Bob Dickerman (Managing Director Enugu Energy Distribution Company) and Engineer Emeka Ezenwanne (Anambra State Commissioner for Public Utilities and Water Resources).


While Speaking at the commissioning, the Vice President remarked that the substation will deliver about 100 Mega Watts of power to the Anambra state capital and its environs. According to him, “The commitment of the administration to ensuring the completion of this Awka NIPP 132KVA grid substation now provides a hitherto unavailable 70MW additional power capacity for driving industrial growth and boosting the economy of the state with positive knock on effect on employment and social-economic upliftment for residents of the state”.


NEWS Engineering’s construction of the substation will increase the spate of Industrialization in the state due to the fact that with improved power supply,, many industries will save cost of self-generation of electricity. This is in tandem with Anambra State Governor, Willie Obianio’s belief that the newly commissioned shoe making factory and cargo airport would be direct beneficiaries of the new substation.


Earlier in his welcome address, Managing Director of NDPHC, Mr Chinedu Ugbo explained that the project is one of the several transmission projects conceived under the National Integrated Power Project (NIPP) being implemented by NDPHC as part of the effort of the Federal Government towards improving electricity transmission in the country. He added ” the Substation is provided with six 33kV feeders to enable robust power evacuation to the following hitherto constrained locations of the EEDC Franchise territory of Anambra State, including two premium new locations critical to the Anambra State Government:


“The Awka Township 33/11kV Injection Substation; the Agu Awka 2unit 15MVA 33/11kV Injection Substation serving the nearby Agu Awka Industrial Layout; the Enugu-Ukwu 33/11kV Injection Substation; the Aguleri/Umuleri 33/11kV Injection Substation; the New Anambra Airport; and the New Awka Millennium City.”


Mr Chinedu Ugbo noted that the substation which was designed and subsequently constructed by NEWS Engineering Nigeria Limited with two 60MVA Transformers, to step down power from the transmission grid at 132KV Level to 33KVA distribution level, as well as a vast array of switchgear and instrumentation transformers and allied equipment. The substation control room comes equipped with standard control and protection equipment to provide adequate and safe control of power flow under both normal conditions as well as during automatically sitting operations when faults occur.


The managing Director/Chief Executive Officer of NEWS Engineering Nigeria Limited, Lady Josephine Nwaeze espoused that the company is an indigenous one that doesn’t compromise quality, and that had erstwhile delivered several other world class projects, with the Newly commissioned substation being one of them. She further remarked; “we want to continue to prove that we have it all here in Nigeria with NEWS Engineering Nigeria limited, a company made up of hundred percent Nigerians. NEWS Engineering Nigeria limited is a company that can deliver reliable and good quality projects” thereby encouraging the Government to make more projects available to indigenous companies to grow the economy in the country.

Read More